Connect Saint Helena Ltd would like to advise the public that as part of their preventative maintenance programme a power outage has been scheduled for Monday 3rd June 2019 from 9am to 2pm, affecting consumers in the following areas, Horse Pasture, Burnt Rock, Woodlands West, Ben Masons, Head O’Wain, and the Seismographic Station. Consumers of Barren Ground, West Lodge, Blue Hill, Gambie’s Gut, High Hill, Thompson’s Wood, Fitzstevens Estate and Horse Ridge will also be affected between 1pm and 2pm.
This scheduled maintenance will allow Connect to reinstate HV lines at Head O’Wain and Ben Mansons. Connect Saint Helena Ltd thank their customers for their patience during this time Connect Saint Helena Ltd would like to advise the public that as part of their infrastructure refurbishment programme, the fifth of six scheduled outages will commence Tuesday 4th June 2019 from 9am to 3pm, affecting consumers in the following areas, Hutt’s Gate, Wells, Alarm Hill, Woody Ridge, Pink Grove and Red Hill - Levelwood.
This scheduled maintenance will allow Connect to continue replacing HV pole insulators from Hutt’s Gate to Red Hill – Levelwood. Connect Saint Helena Ltd thank their customers for their patience during this time. Connect Saint Helena Ltd would like to advise the public that as part of their infrastructure refurbishment programme, a series of four power outages has been scheduled weekly each Thursday. The first of the four scheduled outages will commence Thursday, 30th May 2019 from 9am to 3pm, affecting consumers of Upper Half Tree Hollow from Evergreen Tree, Clinic Drive, White Wall, Half Way, En-Field and High Knoll.
This scheduled maintenance will allow Connect to continue replacing HV pole insulators from Half Tree Hollow to En-Field. Connect Saint Helena Ltd thank their customers for their patience during this time. Connect Saint Helena Ltd would like to advise consumers in Levelwood that there will be a scheduled water interruption on Tuesday 28th May 2019 from 9am to 4pm to install a bulk meter on the water mains. During this period consumers from Sliver Hill to The Kingdom Hall Tank and Red Hill will be without water.
Connect Saint Helena Ltd thank their customers for their patience during this time. Connect Saint Helena Ltd would like to advise the public that as part of their infrastructure refurbishment programme, the fourth of six scheduled outages will commence Tuesday 28th May 2019 from 9am to 3pm, affecting consumers in the following areas, Hutt’s Gate, Wells, Alarm Hill, Woody Ridge, Pink Grove and Red Hill - Levelwood.
This scheduled maintenance will allow Connect to continue replacing HV pole insulators from Hutt’s Gate to Red Hill – Levelwood. Connect Saint Helena Ltd thank their customers for their patience during this time. Connect Saint Helena Ltd would like to advise the public that as part of their infrastructure refurbishment programme a power outage has been scheduled for Thursday 23rd May 2019 from 9am to 3pm, affecting consumers in the following areas, Upper HTH from Evergreen Tree, Clinic Drive, White Wall, Half Way, Prince Lodge, En-Field, High Knoll, Red Hill Vehicle Test Centre, Upper Sapper Way, Red Hill, Gum Woods, Flax Ground and Wood Ground.
This scheduled maintenance will allow Connect to start replacing HV pole insulators from HTH to En-Field and to repair a switch at Flax Ground, St Paul’s Connect Saint Helena Ltd thank their customers for their patience during this time. |